Major traffic delays on I-95 from Fredericksburg to Stafford

Watchful Eye

https://img.particlenews.com/image.php?url=2OwZ05_0fTO69nk00
Photo by Trevor Wrayton, VDOT

VDOT has numerous projects underway that have been causing major delays on I-95 in the Fredericksburg region, and this week will be no exception.

One project involves lifting and installing bridge beams for the future access point to the Express Lanes at the exit 148 interchange. Bridge construction, maintenance and safety inspections are underway, and paving is also being done as part of the I-95 Southbound Rappahannock River Crossing project near exit 130 (Route 3) in Fredericksburg, VDOT announced via media release.

Therefore, over the next few days, drivers will find that both I-95 northbound and southbound will be reduced to one lane near several interchanges between exit 118 (Thornburg) in Spotsylvania County and exit 148 (Quantico) in Stafford County, VDOT forewarned in the release.

VDOT is urging the public not only to plan ahead but also to consider alternate routes, if possible, because the delays are expected to be “major.”

Here is a round-up of traffic changes for May 4 – May 6:

Wednesday, May 4 – Thursday, May 5

· I-95 Southbound at exit 136 (Centreport Parkway) to exit 130 (Route 3)

  • 9 p.m. – 10 a.m. – Single lane closure for mobile paving operations

· I-95 Southbound at Exit 130 (Route 3) Local and Through Lanes

  • 9 p.m. – Single lane closure on both local and through lanes
  • 10 p.m. – Double lane closure both local and through lanes
  • Midnight – 3 a.m. – Entrance or exit ramp closure
  • 4:30 a.m. – Two lanes open, with a single lane closure in place on both local and though lanes
  • 3 p.m. – All southbound lanes open

· I-95 Southbound at exit 118 (Thornburg)

  • 9 p.m. – 10 p.m. – Single lane closure
  • 10 p.m. – 4:30 a.m. – Double lane closure
  • 4:30 a.m. – All northbound lanes open

· Express Lanes Southbound at exit 150 (Joplin Road)

  • 10 p.m. – 4 a.m. – All express lanes southbound traffic will be detoured to general purpose lanes at the interchange.

· I-95 Northbound at exit 118 (Thornburg) and at exit 126 (Spotsylvania)

  • 9 p.m. – 10 p.m. – Single lane closure
  • 10 p.m. – 4:30 a.m. – Double lane closure
  • 4:30 a.m. – All northbound lanes open

· I-95 Northbound at exit 133 (Route 17) to exit 136 (Centreport Parkway)

  • 10 p.m. – 4:30 a.m. – Alternating double lane closures

· I-95 Northbound at exit 143 (Garrisonville Road) to exit 148 (Quantico)

  • 9 p.m. – 10 p.m. – Single lane closure
  • 10 p.m. – 4:30 a.m. – Double lane closure
  • 4:30 a.m. – All northbound lanes open

Thursday, May 5 – Friday, May 6

· I-95 Northbound at exit 143 (Garrisonville Road) to exit 148 (Quantico)

  • 9 p.m. – 10 p.m. – Single lane closure
  • 10 p.m. – Double lane closure
  • 10:30 p.m. – All I-95 northbound traffic will be detoured to the express lanes near exit 143 then shifted back to the regular lanes before exit 148. Tolls will not apply to drivers detoured to the express lanes during this time
  • 4:30 a.m. – All northbound general purpose lanes will reopen.

· Express Lanes Southbound at exit 150 (Joplin Road)

  • 10 p.m. – 4 a.m. – All express lanes southbound traffic will be detoured to general purpose lanes at the interchange.

· I-95 Southbound at exit 126 (Spotsylvania) and at exit 118 (Thornburg)

  • 9 p.m. – 10 p.m. – Single lane closure
  • 10 p.m. – 4:30 a.m. – Double lane closure
  • 4 a.m. – All lanes open

Follow the Watchful Eye on Twitter so you never miss a story!

Did You Know: A Forensics Firm is Expanding, Adding Jobs in Fairfax?

Comments / 5

Published by

Seen. Heard. Reported.

Kilmarnock, VA
1631 followers

More from Watchful Eye

Comments / 0